Boiler required PSV

Status
Not open for further replies.

JM Pagsinohin

Electrical
Nov 15, 2022
1
Hi gentlemen,
I have a question, I just want to ask why we have two PSV required in boiler steam drum? and if it is required by ASME, what specific Section I can find it. Thank you
 
Replies continue below

Recommended for you

It depends on the boiler design code. If ASME I (2021) Section PG-67 stipulates the Pressure-relief Valve requirements.


*** Per ISO-4126, the generic term
'Safety Valve' is used regardless of application or design ***

*** 'Pressure-relief Valve' is the equivalent ASME/API term ***
 
JM Pagsinohin said:
why we have two PSV required in boiler steam drum?
1/ To reduce the probability of failure on demand.
2/ Tradition
 
The reason could be due to a limited relieving capacity of one PSV. To calculate the relieving capacities of PSV's, the ASME Codes for power and heating boilers shows how to calculate those values.
 
To provide more safety, simply. And why? One could go on and on...

DHURJATI SEN
Kolkata, India


 