WRH
Mechanical
- Jun 20, 2002
- 17
We have a user here who has a 10 sheet drawing. Sheet 1 is the assembly of a test stand. On sheet 4 he has a sub-assembly. He wants to put the sub-assembly BOM on sheet 4 which is no problem. On sheet 1 he wants just one balloon in the BOM to call out the sub-assembly. We never did this before so I'm not sure how to go about this. I was thinking we would need to add another repeat region to the main BOM on sheet 1, but what parameters would we use? Is this the right approach? TIA for any help you can provide.
WRH
WRH