MacGruber22
Structural
- Jan 30, 2014
- 802
Have existing masonry plank with existing 2" composite concrete topping. There is a crappy asphalt and waterproofing topping above that is going to be removed. We are replacing with a bonded concrete overlay that will end up with an average thickness of about 3.5 inches and a minimum thickness of 1 1/2" (sloped to drains). Some of the existing composite topping will likely need to be replaced due to extensive water intrusion. At the end of the day, the overlay will be protected with a traffic membrane.
At a minimum, I am going to place crack control joints over beams that support the plank (since there is only a minimum amount of continuity top bars in the existing topping), in addition to typical perimeter isolation joints, etc. We are going to install epoxy mesh in the thicker areas of the overlay. The question I have been pondering over is if contraction joints are warranted for early plastic shrinkage. We typically require an aggregate/cement ratio of at least 5 for repairs which in combination with a low w/c ratio is the best way to limit shrinkage without relying on more expensive compensating additives.
Part of me wants to minimize the number of joints cut into the overlay. More joints, means more sealant, means more maintenance, means more chance for places for water ingress. The other part of me thinks that the average thickness may be too much to not provide contraction joints. Thoughts about the substrate bonding/aggregate interlock restraining early plastic shrinkage? As an extreme example, if my overlay was 6 inches thick, I would be confident in saying the substrate is too far away from the overlay surface is help restraint the early shrinkage - thus requiring a grid of contraction joints within 8-hours of pouring.
One in the hand is worth two in the bush.
At a minimum, I am going to place crack control joints over beams that support the plank (since there is only a minimum amount of continuity top bars in the existing topping), in addition to typical perimeter isolation joints, etc. We are going to install epoxy mesh in the thicker areas of the overlay. The question I have been pondering over is if contraction joints are warranted for early plastic shrinkage. We typically require an aggregate/cement ratio of at least 5 for repairs which in combination with a low w/c ratio is the best way to limit shrinkage without relying on more expensive compensating additives.
Part of me wants to minimize the number of joints cut into the overlay. More joints, means more sealant, means more maintenance, means more chance for places for water ingress. The other part of me thinks that the average thickness may be too much to not provide contraction joints. Thoughts about the substrate bonding/aggregate interlock restraining early plastic shrinkage? As an extreme example, if my overlay was 6 inches thick, I would be confident in saying the substrate is too far away from the overlay surface is help restraint the early shrinkage - thus requiring a grid of contraction joints within 8-hours of pouring.
One in the hand is worth two in the bush.