Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Book on ASME VIII DIV 1 2

Status
Not open for further replies.

AnEngineer

Mechanical
Feb 24, 2003
20
I want to buy a book on PV (Designer's Handbook type with worked out examples) explaining necessary sections of ASME VIII div 1 in a nut shell.

A recommendation (book's name & author) from user's point of view will be appreciated.
 
Replies continue below

Recommended for you

Here are several good technical books on this subject (I have all three books);

1. "Pressure Vessel Design Handbook" by Henry H. Bednar (one of the best on pressure vessel design with examples)

2. "Pressure Vessels" by R. Chuse and B Carson (simplified applications of ASME Section VIII, Div 1).

3. If you are really interested in theory;

"Theory and Design of Modern Pressure Vessels" by John Harvey
 
I also forgot to mention one other source that may be of help with ASME Section VIII Div 1 examples, the CASTI book series;

 
metengr makes some excellent recommendations. I would also suggest:

4. "Pressure Vessel Design Manual" by Dennis Moss.
 
I recommend CASTI, which is more focussed on ASME VIII. Bednar is good for the cases not covered fully by the ASME code.

Putting Human Factor Back in Engineering
 
shop inspection for PWHT and after PWHT Postweld Heat Treatment

This operation can be defined as the heating of weldments immediately after welding in order to temper, stress relieve, or provide controlled cooling. It prevents the formation of hard or brittle structures prone to cracking in services. Postweld heat treatment is mandatory for certain alloys, combinations or alloys, and material thicknesses as outlined in the various codes and standards, such as ASME Section VIII Pressure Vessel Code. Consequently, welding procedures for such materials and/or thickness will contain the provisions for heat treatment.



Fabricators may have difficulty with prostweld heat treatment due to shop practices rather than the treatment itself. Cracking can occur in vessels that are held for heat treating until a full furnaces load is ready.



In general, at normal heat treating temperatures the time at temperature is specified as one hour per 1 in. (25 mm) of maximum thickness for vessels up to 2 in. (50 mm) thickness fabricators may suggest that since the component is being heated form both sides half-an-hour at temperature for each 1 in. (25) thickness is sufficient – but the one hour requirement should be maintained.



For vessels over 2 in (50 mm) in thickness, the usual holding time is two hour plus 15 minutes for each additional 1 in. (25 mm) over the 2 in. (50 mm) thickness. Again, some fabricators may want to cut this time by half since the component is being heated form all sides.



Holding time may be an accumulation of multiple heat-treat cycles. It dose not necessarily have to occur all at one time. Care must be taken to ensure that the accumulated time at the correct temperature equals that required to effect the desired treatment.



There is a maximum furnace temperature for introduction of the vessel. This varies with the alloy but is generally 800º F (426º C) for carbon steels. Heating rate vary with alloy as well but are usually in the 200 to 400º F (93 to 204º C) range. Some manufactures will try to heat as rapidly as possible in order to reduce the time required.



Cooling is normally performed in the furnace at a controlled rate unless the component si to be quenched. If quenching is performed then the component must be removed form the furnace and quenched as quickly as possible. Delays will cause such problems as carbide precipitation in austenitic alloy and reheat treatment will be necessary.
 
Thank you gents for your recommendations. Much appreciated.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor