muuddfun
Geotechnical
- Feb 4, 2008
- 107
Does anyone have experience with bore and jack of pipes (24 inch water line)in conditions with cobles and occasional boulders? I reviewed most of the posts on the board on this subject but they were a little different than the sittuation I have.
I have a project with a 24 inch wateline that needs to cross under 48 inch RCP storm drains for about 100 feet. The civil does not want to cut the storm drains and do an open cut, he believes it would still be cheaper to do some pipe jacking. Storm drains are dry 99 percent of the year so diversion of storm water would not be of much concern.
The bottom of the storm drains are about 10 feet below the roadbed. The soils are sand with gravel, cobbles and the occasional boulder. Cobles are about 5 to 15 percent by volume, and the occasional boulder was encountered in my borings. I drilled 3 borings near the location and one terminated at 12 feet on a boulder, and the other 2 were able to get to 30 feet depth with some difficulty. The borings caved to about 7 feet after pulling the augers. There is not groundwater. Most of the borings I drilled for this project terminated on a large cobble or boulder at some point before the planned depth.
I am concerned about groundloss around the bore and jack operation, and how to get past any cobbles or boulders without to much expense, any guidance or experiences anyone could share would be appreciated. I am thinking about grouting first, but if it could be done without?? Any ideas.
Thanks
I have a project with a 24 inch wateline that needs to cross under 48 inch RCP storm drains for about 100 feet. The civil does not want to cut the storm drains and do an open cut, he believes it would still be cheaper to do some pipe jacking. Storm drains are dry 99 percent of the year so diversion of storm water would not be of much concern.
The bottom of the storm drains are about 10 feet below the roadbed. The soils are sand with gravel, cobbles and the occasional boulder. Cobles are about 5 to 15 percent by volume, and the occasional boulder was encountered in my borings. I drilled 3 borings near the location and one terminated at 12 feet on a boulder, and the other 2 were able to get to 30 feet depth with some difficulty. The borings caved to about 7 feet after pulling the augers. There is not groundwater. Most of the borings I drilled for this project terminated on a large cobble or boulder at some point before the planned depth.
I am concerned about groundloss around the bore and jack operation, and how to get past any cobbles or boulders without to much expense, any guidance or experiences anyone could share would be appreciated. I am thinking about grouting first, but if it could be done without?? Any ideas.
Thanks