If the pile toe levels has been exceeded by more than 500mm or so, what is the best rectification for this:
I have thought about a few options but advise would be great:
* pour in concrete to the toe level
* do nothing as the desirable toe level has been passed and therefore has met the piling requirement.
Any ideas would be greatly appreciated.
Thanks
AKE
I have thought about a few options but advise would be great:
* pour in concrete to the toe level
* do nothing as the desirable toe level has been passed and therefore has met the piling requirement.
Any ideas would be greatly appreciated.
Thanks