Allan18172
Structural
- Apr 11, 2003
- 2
I am work on a church that has 90' high walls around the perimeter. The first 22' are 18" thick the rest is 12" thick. The first lift to 22' will be installed and then the structural steel will be installed, then the walls will continue to full height. These walls need to be temporarily braced to handle wind and construction loading. We are considering using wire rope tied anchored to the ground on each side of the wall. Is this a feasable application, or does anyone have any have any knowledge of this type of application.