I am installing a truss bridge in Montana and I am trying to find a design for an abutment that doesn't have piling, just a spread footer.
The bridge is 75' long and spans the high water mark by 12' on either side so I shouldn't have any scouring.
The soil is rocky but not bedrock.
I need to be able to drive concrete trucks across the bridge.
How deep and wide does the footer need to be?
Do I need any other structural concrete in the ground if I don't plan on having any wing walls?
The bridge is 75' long and spans the high water mark by 12' on either side so I shouldn't have any scouring.
The soil is rocky but not bedrock.
I need to be able to drive concrete trucks across the bridge.
How deep and wide does the footer need to be?
Do I need any other structural concrete in the ground if I don't plan on having any wing walls?