n8engr
Structural
- Mar 2, 2001
- 22
I am working on a project to upgrade an existing crane rail system to a higher capacity.
The question I have is regarding the Longitudinal or Tractive force load. AISE states it is equal to 20 percent of the maximum load on driving wheels. Let's say for example my tractive force load is 0.2*45k wheel load=9k. Is that 9k load applied at each wheel or distributed amongst them.
This existing crane has two trucks with two wheels on each truck for a total of four wheels on each side. Right now I am using the tractive force load = 9k per wheel or 36k per side. Should it only be 9k/4 wheels=2.25k per wheel?
Thanks for the help...
The question I have is regarding the Longitudinal or Tractive force load. AISE states it is equal to 20 percent of the maximum load on driving wheels. Let's say for example my tractive force load is 0.2*45k wheel load=9k. Is that 9k load applied at each wheel or distributed amongst them.
This existing crane has two trucks with two wheels on each truck for a total of four wheels on each side. Right now I am using the tractive force load = 9k per wheel or 36k per side. Should it only be 9k/4 wheels=2.25k per wheel?
Thanks for the help...