facca
Civil/Environmental
- Mar 27, 2004
- 37
We are a contractor on a small bridge project which requires a 7" bridge deck slab to be removed & replaced between the existing cast-in-place girders.The bid design shows a temporary support structure at mid span of these existing girders with no stated bearing requirement.My falsework engineer has stated that we do not require a support at mid span due to the fact that the new deck is similar to the replaced one and that if it supported the old deck they will support the new deck.We have asked the designer to provide us with the bearing requirements for these supports and they have not been provided after 5 weeks and repeated requests.What is our next step?