Hi All,
I am currently working on a bridge structure and there are a few concerns we have with respect to the deck waterproofing. Namely, the grade of the structure (almost 10% at the steepest section), temperature during construction of this phase (might be lower than 10 degrees Celsius) and the vehicle traffic loading (specifically the dump trucks for the asphalt). Any feedback would be greatly appreciated. Thanks!
I am currently working on a bridge structure and there are a few concerns we have with respect to the deck waterproofing. Namely, the grade of the structure (almost 10% at the steepest section), temperature during construction of this phase (might be lower than 10 degrees Celsius) and the vehicle traffic loading (specifically the dump trucks for the asphalt). Any feedback would be greatly appreciated. Thanks!