BUDGET ESTIMATES FOR BUILDING UTILITIES

Status
Not open for further replies.

cfordyce

Electrical
Jun 26, 2002
55
0
0
CA
Hello. I was wondering if there are posted or recommended budget numbers for utilities costs for a large facility (manufacturing). If they exist, I assume they would be dependant on the seasonal weather conditions experienced in that area. (I'm in Ontario - about 50%-50% summer-winter balance)
e.g. large 250,000 sq ft manufacturing plant

I was looking for something like:
1. lighting costs per sq ft of floor space
2. heating costs for same. Natural gas.

Any information you may have would be helpful.

Thanks.

CAF
 
Replies continue below

Recommended for you

cfordyce,

I can only help with European installation cost ratios from the 2006 edition of the Prijzenboekje:

lighting
250 lux .... from 20 to 27 EUR/m2
500 lux .... from 37 to 48 EUR/m2
750 lux .... from 48 to 64 EUR/m2
1000 lux ... from 59 to 75 EUR/m2

emergency lighting ... from 10 to 13 EUR/m2

heating depends on the cubic meters of the building;
for manufacturing buildings assume between 11 and 16 EUR per m3

Kind Regards,
hahor
 