engOFFG
Structural
- Aug 5, 2015
- 7
Dear Experts,
I have 6 stories building (of total height 31m) , with big plan area
divided by several parts , each part of 100mx100m
between each 2 parts I calculated seismic joints, based on UBC97 , ACSE7-2010 , and IBC2012
results are similar, and give unreasonable gap width ( separation) closed to 140mm to 200mm.
for example(UBC);
for first part I get delta-s (joint displacement)from etabs from case SPECx( response spectrum ,x-dir.)
then get delta-m = delta-s X 0.7 X R
where R=5.5
then get the same for the second part
then apply code equation, and get very conservative separation width.
IS this way I followed OK?
any ideas to get reasonable value?
(see attached UBC97 equation)
I have 6 stories building (of total height 31m) , with big plan area
divided by several parts , each part of 100mx100m
between each 2 parts I calculated seismic joints, based on UBC97 , ACSE7-2010 , and IBC2012
results are similar, and give unreasonable gap width ( separation) closed to 140mm to 200mm.
for example(UBC);
for first part I get delta-s (joint displacement)from etabs from case SPECx( response spectrum ,x-dir.)
then get delta-m = delta-s X 0.7 X R
where R=5.5
then get the same for the second part
then apply code equation, and get very conservative separation width.
IS this way I followed OK?
any ideas to get reasonable value?
(see attached UBC97 equation)