SteelPE
Structural
- Mar 9, 2006
- 2,759
I am currently looking at a project where the building will be put under negative pressure. The reason for this is so the client can make sure the air that leaves the facility is properly filtered/cleaned. I am wondering how this would be handled in regards to building loading? I am guessing that you would just need to manipulate GCpi in some way, but I am wondering what the proper approach is. Are there any recommendations on how to handle this situation within ASCE-7?