Hey Guys,
I have 11.4m joists with concrete floor finishing, and i am thinking of using a composite system, the thing is we are a PEB fabricator and we simply love the Built up Sections.
did any body ever use a composite system with built up sections, we usually use one side welding between the web and flange but i am thinking with the high transfer load value on the flange this could be a problem?
any suggestions, hints, ideas or concerns on this ?
ôIf you don't build your dream someone will hire you to help build theirs.ö
Tony A. Gaskins Jr.
I have 11.4m joists with concrete floor finishing, and i am thinking of using a composite system, the thing is we are a PEB fabricator and we simply love the Built up Sections.
did any body ever use a composite system with built up sections, we usually use one side welding between the web and flange but i am thinking with the high transfer load value on the flange this could be a problem?
any suggestions, hints, ideas or concerns on this ?
ôIf you don't build your dream someone will hire you to help build theirs.ö
Tony A. Gaskins Jr.