I have a tough question on a project I am working on. We are using concrete pile foundation with shorecrete wall to retaining soils. Retaining height varies from 8ft to 25ft....I am using 24'' to 30'' concrete pile with steel W beam in the middle. Basically it is a soldier pile but it is not temporary.
There are huge moments at the base (assuming it is a cantilever columns embeded into soils). Steel beam is very large if considering steel bending capacity only. I am thinking to use the composite section but do not know how to model this section in SAP2000.
Does any engineer here know how to model concrete pile section with W beam in the middle? Thank you very much.
There are huge moments at the base (assuming it is a cantilever columns embeded into soils). Steel beam is very large if considering steel bending capacity only. I am thinking to use the composite section but do not know how to model this section in SAP2000.
Does any engineer here know how to model concrete pile section with W beam in the middle? Thank you very much.