HotStab
Mechanical
- Jul 10, 2007
- 29
I am working on the design of subsea pipeline equipment: PLETs and In-line ESDV Sleds. PLETs shall be connected to rigid pipes, but In-Lines shall be between flexible flowlines. They shall be installed at depth up to 2000 meters.
Due to lay-out configuration, for all assemblies the center of gravity will be above the center lines of pipeline connection flanges. During installation or recovery of In-Lines, or PLETS in first extremity, this high COG shall impose an undesirable torsion in the pipeline.
To eliminate this problem counter weight should be added to the bottom part of the assemblies. Or buoyancy shall be attached to the top of the structure.
As far as I could see, the first alternative is not a good one, because buoyancy should be required anyway to compensate the dead load of equipment and reduce the bending moments it impose in pipeline. The use of counter weight will increase the dead load, and will imply in more buoyancy required. Other collateral effect: extra weight would demand more foundation area.
Please, I need help to understand:
1- Could In-Line equipment be installed without buoyancy?
2- Is it possible to install a PLET at first extremity without buoyancy?
3- How to evaluate the buoyancy quantity required?
4- Is lowering the COG using counter weigh a valuable approach?
5- Which are the main considerations that should be take in account for rigid and flexible pipeline installation?
6- Can rigid pipelines be installed at 2000 meters by S-lay method?
7- Which are the special requirements that should be considered in equipment design regarding different installation methods (S-lay and J-lay)?
Unfortunately, we have no access to the installation contractor. So, I would appreciate your help very much.
Due to lay-out configuration, for all assemblies the center of gravity will be above the center lines of pipeline connection flanges. During installation or recovery of In-Lines, or PLETS in first extremity, this high COG shall impose an undesirable torsion in the pipeline.
To eliminate this problem counter weight should be added to the bottom part of the assemblies. Or buoyancy shall be attached to the top of the structure.
As far as I could see, the first alternative is not a good one, because buoyancy should be required anyway to compensate the dead load of equipment and reduce the bending moments it impose in pipeline. The use of counter weight will increase the dead load, and will imply in more buoyancy required. Other collateral effect: extra weight would demand more foundation area.
Please, I need help to understand:
1- Could In-Line equipment be installed without buoyancy?
2- Is it possible to install a PLET at first extremity without buoyancy?
3- How to evaluate the buoyancy quantity required?
4- Is lowering the COG using counter weigh a valuable approach?
5- Which are the main considerations that should be take in account for rigid and flexible pipeline installation?
6- Can rigid pipelines be installed at 2000 meters by S-lay method?
7- Which are the special requirements that should be considered in equipment design regarding different installation methods (S-lay and J-lay)?
Unfortunately, we have no access to the installation contractor. So, I would appreciate your help very much.