Hello,

Happy 2007!

As you may know many governments give tax credits for R & D hours in a project.

Not all the hours in a task or a project are R & D.

We would like to calculate how many hours were spent doing R & D in a particular project. Some of the tasks qualify as R & D and some do not.

Is there a way to "flag" the tasks that are R & D so that we can get the sum of all our R & D hours?

Thanks,

Joseph
 
Replies continue below

Recommended for you

Why can't you add a text column that flags your R&D tasks and the filter on that flag?

TTFN



 

Thank you IRstuff, this works perfectly.

One more question, once you have the filter is there a way to automatically add up all hours in the work column in MS Project?

cheers,

Joseph
 
Wel,, the cheap date is to copy the filtered data into Excel and sum it.

A more algorithmic solution is to use yet another field and customize it to report the cost for those items that you want, e.g., if(text1="a", cost, 0), then set the rollups for that column to sum.

TTFN



 

Many thanks IRstuff, your advice works great and is valued.