justbuildit
Civil/Environmental
- Oct 25, 2005
- 17
I am trying to estimate how many tons of riprap per neat cubic yard of placement. I am thinking along these lines:
1) Determine riprap density from source...assume 155 lbs/ft3 in this case. That's about 2.09 tons/cy of 'rock'
2) Now the part I need someones experience on is how much void to factor in. If voids account for 33% of the total volume then this reduces to 1.5 tons per 'neat' cy. I realize this can vary, but what we have to use something. I think the void ratio would also vary by what size of riprap is being placed. What void ratio would you use for the
a) 1/4 ton riprap
b) 1 ton riprap
c) 3 ton riprap
d) 6 ton riprap
3) I would also use this information to determine the quantity of concrete used to fill the voids if placing concreted riprap.
Thanks for your help
1) Determine riprap density from source...assume 155 lbs/ft3 in this case. That's about 2.09 tons/cy of 'rock'
2) Now the part I need someones experience on is how much void to factor in. If voids account for 33% of the total volume then this reduces to 1.5 tons per 'neat' cy. I realize this can vary, but what we have to use something. I think the void ratio would also vary by what size of riprap is being placed. What void ratio would you use for the
a) 1/4 ton riprap
b) 1 ton riprap
c) 3 ton riprap
d) 6 ton riprap
3) I would also use this information to determine the quantity of concrete used to fill the voids if placing concreted riprap.
Thanks for your help