Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

Calendars in Microsoft Project

Status
Not open for further replies.

e74222

Civil/Environmental
Oct 9, 2009
3
0
0
HK
Dear,

I used to set in the file/ options / schedule : default start time, default end time , hours per day, hours per week , days per month at the very beginning . Then I set up different calendars for different tasks. However, some calendars may have different start time, end time hours per week with previous file/ option setting. This would come out with duration in decimal places. Please advise.


Regards,


Gary Lo
 
Replies continue below

Recommended for you

Status
Not open for further replies.
Back
Top