Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Can a contractor use a WPS used on

Status
Not open for further replies.

fain33

Petroleum
Mar 18, 2009
1
Can a contractor use a WPS used on a different project/production

I have a contractor that wants to use an previously approved WPS he used with our company on a recent project because the pipe sizes are similar. The contract weld code is ASME B31.12 which follows the AWS.

My question is; is this OK and acceptable following the code?


 
Replies continue below

Recommended for you

As long as the WPS falls within the range of a qualified PQR which meets the requirements of B31.12, yes, provided the requirements of GR-3.2.3 are met.
 
If it was previously approved why would it not be now ?
If the new pipework complies with all the variables (essential and non essential) of the original approved WPS then you are good to go.
Regards,
DD
 
Yes. A qualified WPS can be used for multiple projects over a prolonged period of time as long as it meets contract and Code for the work performed.
 
I can think of a couple of reasons why a WPS that was approved for a previous project might not be appropriate for a current project, post weld heat treatment or notch toughness. The WPS is not qualified for either PWHT or notch toughness and the new project has requirements for either.

Best regards - Al
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor