NX 8.5 Does anyone know if I can add a 2nd, 3rd etc vertex to a hole call out leader or a note leader?
Thanks
 
Replies continue below

Recommended for you

a note: yes
a hole callout: no

On the note menu expand List and then click on New
 
If you use a note, simply double click the leader. In the note dialog under leader you will see a button that says 'specify jog position' click that and then click where you want the leader to 'break'. You can add as many jog positions as you would like.
 