I have this cantilever steel beam with overhead connection with a concrete slab - see attached sketch-. The end forces on the beam are:
M(Major) = 119 kN.M,
M(Minor) = 37 kN.M,
Shear (Major) - which will act as tension on the connection= 44 kN
Shear (Minor) = 76 kN.
My concern is how the distribution of tension on bolts would be like?, would it be OK if i treated as a base plate? or should I consider the first 2 bolts to carry the whole tension? or maybe half the bolts?
I tried to use mechanical Hilti bolts HSL-3 M24 and the ratio is OK, but I'm dealing with it as a base plate connection.
Any ideas guys? your help would be appreciated
Thanks in advance
M(Major) = 119 kN.M,
M(Minor) = 37 kN.M,
Shear (Major) - which will act as tension on the connection= 44 kN
Shear (Minor) = 76 kN.
My concern is how the distribution of tension on bolts would be like?, would it be OK if i treated as a base plate? or should I consider the first 2 bolts to carry the whole tension? or maybe half the bolts?
I tried to use mechanical Hilti bolts HSL-3 M24 and the ratio is OK, but I'm dealing with it as a base plate connection.
Any ideas guys? your help would be appreciated