Hello -
Quick generic questions
2 Shifts , each one is 8 hours / day with 1 hr breaks
Process 1 : 10 Sec Cycle Time, FPY of 90%, Yield of 95%, Availability : 85%, Performance, 85%
Process 2 : 10 sec Cycle Time, FPY of 85%, Yield of 95%, Availability : 85%, Performance, 85%

1 - What is the Tput Rate of Process 1 ?
2 - What is the capacity of Process 1 ?
3 - What is the effective Tput Rate of Process 1
4 - What is the effective capacity of Process 1
5 - What is the bottleneck of the line and why ?
6 - What is the line Capacity and Tput Rate

Thanks for all your help
 
Replies continue below

Recommended for you

Thanks for answering,
I'm puzzled, I'm asking for help, it's not a homework, this is a real life scenario and I'm seeking answers. Should it still be put to another forum ?

Thanks
 
this depends on your definitions of the terms.

How is yield different from FPY?
How is throughput defined?
How is capacity defined?
How is performance defined?


How are Process 1 and Process 2 related, since there are no questions related to Process 2?