AndrewM7
Industrial
- Feb 13, 2007
- 3
Anyone with good insight on heat treating investment cast 17-4. Most recipes I’ve looked at, of course, start with the material at Condition A (annealed) from the mill. I’ve also seen the anneal processed outlined, 1950 ± 25°F (1066 ± 14°C) for ½ hr, but is it necessary for cast parts, and how critical is the temp? The part requires a tight balance of yield strength, impact strength, fatigue, and resistance to fracture witch we had originally. It’s small part with a service temp potential dipping to -50°C, so I need to avoid brittle fracture. In a switch from Oil quench to Air quench I’m able to sustain hardness values, but they are NOT correlating to good yield strength, i.e. failing in torsion.
Currently using this, basically what the heat treat facility pulled out and like I said hardness values are within H925 range (desired…), but failing yield strength.
1. Homogenize ~1150° C +0/-10 - 120min (Higher temp and longer than what I’ve seen suggested, Could this be my greatest issue?)
2. Cool - Temp below 30° C
3. Solution Heat treat 1040° C - 60min (This is also much longer than I’ve seen suggested…)
4. Air Quench below 30° C
5. Precipitation hardening 500+/-5° C*90min (Shooting for H925 condition, this should be adjusted to 4 hours, but they adjusted to reach desired hardness)
6. Cool to room temp
I guess in outlining this I’ve realized some obvious process changes I need to correct, and will start with the times and temps of process 1 and 3, but if there are suggestions on the following I could use them…
A. Is the Homogenize (to Condition A, step 1) critical for cast 17-4?
B. Is excessive time and temp at Homogenize promoting an undesired ‘grain growth’ issue?
Thanks
Currently using this, basically what the heat treat facility pulled out and like I said hardness values are within H925 range (desired…), but failing yield strength.
1. Homogenize ~1150° C +0/-10 - 120min (Higher temp and longer than what I’ve seen suggested, Could this be my greatest issue?)
2. Cool - Temp below 30° C
3. Solution Heat treat 1040° C - 60min (This is also much longer than I’ve seen suggested…)
4. Air Quench below 30° C
5. Precipitation hardening 500+/-5° C*90min (Shooting for H925 condition, this should be adjusted to 4 hours, but they adjusted to reach desired hardness)
6. Cool to room temp
I guess in outlining this I’ve realized some obvious process changes I need to correct, and will start with the times and temps of process 1 and 3, but if there are suggestions on the following I could use them…
A. Is the Homogenize (to Condition A, step 1) critical for cast 17-4?
B. Is excessive time and temp at Homogenize promoting an undesired ‘grain growth’ issue?
Thanks