structuralsteelhead
Structural
- Apr 13, 2010
- 62
Tasked with designing a cast in place wet well structure. 37 feet deep, 12' by 17' Not sure the reasoning this was not sent out to pre-caster, but that ship has sailed and I was not part of the reasoning why I'm asked to design a cast in place option. Typically the pre-caster would form sections in his plant and ship. I'm considering doing the same with a cast in place option having the contractor pour two or three separate sections and form the top and bottom joint similar to how a pre-cast company might, maybe it would require more sections. Not sure on the means and methods side here but I do need to address it. I don't want to just show a monolithic detail of the wall structures and call it a day. Or should I?
Not sure how thick the walls will be, assuming 10"...waiting for geotech report design parameters. I'm sure forming blowout will be an issue, so even if formed full height, I'm sure there would be a limit in height and thus a construction joint necessary. The wet well/lift structure is for storm water, not sewer by the way.
Penny for your thoughts for those designing these on a day to day basis. (Although I know and respect these thoughts worth a little more than a penny!) Thanks in advance nonetheless for your grossly underpaid thoughts.
Not sure how thick the walls will be, assuming 10"...waiting for geotech report design parameters. I'm sure forming blowout will be an issue, so even if formed full height, I'm sure there would be a limit in height and thus a construction joint necessary. The wet well/lift structure is for storm water, not sewer by the way.
Penny for your thoughts for those designing these on a day to day basis. (Although I know and respect these thoughts worth a little more than a penny!) Thanks in advance nonetheless for your grossly underpaid thoughts.