rcm87
Civil/Environmental
- Feb 23, 2011
- 6
Hi. At work I'm currently preparing for casting a slab, and the following doubt arised.
One of the beams is a 1m tall beam which starts from the slab and goes up. The slab is a "waffle slab" of 20cm thickness.
The engineer which made the structural design, told us that it is OK to first cast the 20cm of the slab, and the next day we can proceed with casting the other 80cm of the beam.
He sustains this because the beam has continuous stirrups along all the length.
Is this a correct procedure?
Thanks. And sorry if my english isn't the best. I would gladly re-post anything that might not be clear.
One of the beams is a 1m tall beam which starts from the slab and goes up. The slab is a "waffle slab" of 20cm thickness.
The engineer which made the structural design, told us that it is OK to first cast the 20cm of the slab, and the next day we can proceed with casting the other 80cm of the beam.
He sustains this because the beam has continuous stirrups along all the length.
Is this a correct procedure?
Thanks. And sorry if my english isn't the best. I would gladly re-post anything that might not be clear.