010185
Civil/Environmental
- Dec 2, 2005
- 7
A foundation on which a pylon is to be built so that the pylon structure can be placed directly onto it once it's completed.
On the top surface of the foundation (Surface area = 4.5m x 4.5m) 24 holding down BOLTS of length 1000mm are to be CAST VERTICALLY with 800mm of their lengths into the concrete.
The finished LEVEL OF BASE IS TO ACCURATELY ALIGN with the floor of the pylon and the tolerance is +/-3mm.
The location of the bolts is critical; there is only +/-2mm clearance in the pylon bases and all bolts must be 100% vertical.
Can anyone suggest a method of construction which ensures the requirements?
On the top surface of the foundation (Surface area = 4.5m x 4.5m) 24 holding down BOLTS of length 1000mm are to be CAST VERTICALLY with 800mm of their lengths into the concrete.
The finished LEVEL OF BASE IS TO ACCURATELY ALIGN with the floor of the pylon and the tolerance is +/-3mm.
The location of the bolts is critical; there is only +/-2mm clearance in the pylon bases and all bolts must be 100% vertical.
Can anyone suggest a method of construction which ensures the requirements?