Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

CFA and reinforcement

Status
Not open for further replies.

steveyeung

Civil/Environmental
Sep 5, 2004
76
I am working on a bridge project and the foundation is that: bored piles of 600mm diameter will rest on clalk which is covered a 12m thick soft made ground. A geotechnical engineer said "it would be difficult to lower (the bottom of) a reinforcement cage deep down to the pile base if the pile is socketed into the chalk by 3m and the hole is bored by a CFA."

Could geot guy tell me why???
 
Replies continue below

Recommended for you

A continuous flight auger must be removed from the excavation before placing the reinforcement. The hole will collapse or slough in causing the cage to set on spilled soil. A casing left in plce will prevent the problems associated with soft soils and sloughing. Some proceedures remove the casing as the the concrete is filling the pile volume, but I recommend that it stay in place.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor