stan000
Mechanical
- Jul 31, 2014
- 121
when there is a change in the nonessential variable in wps, i produce a new WPS but without performing a new PQR.
my understanding It is the manufacturer quality control team and third party inspector task, to check and make sure that welding procedure specification is completely consistent with actual welding job that is in the progress on the shop floor i.e. joint design, filler wire type and diameter, inert gas type and flow rate, voltage, and amperage, preheat and inter-pass temperature, etc.
do i have to show new wps to T.S.S.A OR Authorized inspector.
i was looking in API But i didn't find out.
regards
my understanding It is the manufacturer quality control team and third party inspector task, to check and make sure that welding procedure specification is completely consistent with actual welding job that is in the progress on the shop floor i.e. joint design, filler wire type and diameter, inert gas type and flow rate, voltage, and amperage, preheat and inter-pass temperature, etc.
do i have to show new wps to T.S.S.A OR Authorized inspector.
i was looking in API But i didn't find out.
regards