Hi,
when the anticipated temperature (ambience or media) in an oil and gas facility is not going to go below -20F is Charpy impact testing required for the weld procedure?
1. For API wellhead welding to ANSI line pipe, MDT above at -20F
2. Same as 1 above but MDT below -20F
3. B31.3, 31.4, or 31.8 piping with MDT above -20F
4. Same as 3 above with MDT below -20F
I am under the impression from my little knowlege of the code that impact testing is required only for 2 and 4 above, is that right?
If so, how does one determine the test temperature?
Thanks a lot.
when the anticipated temperature (ambience or media) in an oil and gas facility is not going to go below -20F is Charpy impact testing required for the weld procedure?
1. For API wellhead welding to ANSI line pipe, MDT above at -20F
2. Same as 1 above but MDT below -20F
3. B31.3, 31.4, or 31.8 piping with MDT above -20F
4. Same as 3 above with MDT below -20F
I am under the impression from my little knowlege of the code that impact testing is required only for 2 and 4 above, is that right?
If so, how does one determine the test temperature?
Thanks a lot.