We are proposing to connect a 4" force main to an existing 14" force main. Based on old design plans, the 14" force main is operating at 1,600 GPM @ 216' TDH (two submersible 130 HP pumps). Our proposed lift station will operate at 100 GPM @ 50' TDH. We are proposing to add two check valves on either side of the MJ at the force mains connection. QUESTION: Assuming the p.stations can both operate at the same time, will the check valves actually function/open up against the pressure of the opposing force main flow? In other words, if the 14" force main is running at the aforementioned flow, will the 4" check valve open once the smaller proposed pump station is in operation?