Hi ,
i need to clarify some thing , i have a main chilled water supply and chilled water return pipe on roof top , this main pipe's are feeding 24 typical shafts .
i have 4 floors , when the risers reaches after distribution to last floor at the end ( since i have a Closed loop they are connected to each other )
now i have to provide a drain connection for the risers ( in case of maintenance ) i use a tee @ the center[highlight #CC0000] ( please Check the attachment )[/highlight] and a ball valve and plus when the main pipe on roof top take's a branch for 1 shaft i have gate valves ,
please check the attachment for image and give me your valuable comments if this design is ok or i need to add more valves or i missed some thing
thanks
i need to clarify some thing , i have a main chilled water supply and chilled water return pipe on roof top , this main pipe's are feeding 24 typical shafts .
i have 4 floors , when the risers reaches after distribution to last floor at the end ( since i have a Closed loop they are connected to each other )
now i have to provide a drain connection for the risers ( in case of maintenance ) i use a tee @ the center[highlight #CC0000] ( please Check the attachment )[/highlight] and a ball valve and plus when the main pipe on roof top take's a branch for 1 shaft i have gate valves ,
please check the attachment for image and give me your valuable comments if this design is ok or i need to add more valves or i missed some thing
thanks