nhcf
Electrical
- Oct 22, 2014
- 74
I observed an existing installation - 480/277 VAC wye generator, 1KW, operating in parallel with facility distribution/utility. It appeared the neutral in the generator was bonded to ground. It also appeared (based on site drawings) that utility transformer N was also bonded. Generally only one bond permitted -is this different for a generating facility or should one of the two bonding jumpers be removed?