Just finished manufacturing a pressure vessel in Chrome Moly material including PWHT. Prior to hydro the client wants to add a welded earthing boss to the foot of the vessel i.e. not the pressure envelope.
Would I be ok to preheat the area of welding and the boss then weld as per my wps with slow cooling under a thermal blanket without having to do a PWHT on the whole vessel? My instincts tell me the weld is external, small in size (5mm fillet) and not going to see service fluids. The weld procedure for the fillets has already seen a 100 percent pass rate on all other welds under radiography.
Any help would be greatly appreciated.
Many thanks
Brian
Just finished manufacturing a pressure vessel in Chrome Moly material including PWHT. Prior to hydro the client wants to add a welded earthing boss to the foot of the vessel i.e. not the pressure envelope.
Would I be ok to preheat the area of welding and the boss then weld as per my wps with slow cooling under a thermal blanket without having to do a PWHT on the whole vessel? My instincts tell me the weld is external, small in size (5mm fillet) and not going to see service fluids. The weld procedure for the fillets has already seen a 100 percent pass rate on all other welds under radiography.
Any help would be greatly appreciated.
Many thanks
Brian