esass13
Civil/Environmental
- Sep 14, 2004
- 41
What is a good time frame for completing CIPP work? How much can a CIPP contractor complete in a day's time? Does it depend on the services more than anything? My assumption is a contractor could reline 500 feet or so in a day including replacing about 10 services from cleanout to new connection to CIPP. We are replacing services and I'd rather make a clean new service tap than doing an internal robotic cutter and then connecting the new service to whatever roundish hole the robot cut. I'm thinking of using an Inserta-Tee so the hole needs to be round.
Any ideas? Thanks
Any ideas? Thanks