J1D
Structural
- Feb 22, 2004
- 259
In pile design, 10M (approx #3) @12” ties are usually specified (from what I know) regardless of pile diameter, etc. I wonder if this is always good from you experience? And the ties are cut with certain overlap (e.g. 16”) only, no hooks! This has bugged me for a while. From the function of transverse rebar, the hook is definitely required in column, but for piles because of the soil restraint …… What do you think?