civil deliverables in EPC project

Status
Not open for further replies.

sfmech

Mechanical
Apr 10, 2007
17
In an Engg. Procurement and Construction project, what the the deliverables produced by the Civil Engg. department during FEED and Detailed Engg. I know foundation drawings and civil works specification. What are the others.
 
Replies continue below

Recommended for you

Depends on the project as well as the EPC firm, but here are typical details.

Civil Deliverables:
Site Development, Layout and Planning
Site Grading and Drainage
Sedimentation and Erosion Control Plans
Underground Piping Plans
Railroad Design
Stormwater Quantity and Quality Control
Federal, State and Local Permitting and Code Compliance
Construction Contract Bid Packages / Specifications, Including Permit Packages

Structural Deliverables
Structural Steel Design
Structural Analysis, Including Dynamic Loading
Foundation Design, Including Common, Complex and Deep
Sheet Piling, Piling, and Caisson Design
Concrete Design
Masonry Design
Timber Design
Damage Assessment and Repair Design
State / Local Permitting and Code Compliance Studies / Design
Construction Contract Bid Packages / Specifications, Including Permit Packages
Plant Record Drawings





 
survey
geotechnical
roads paving and traffic
fencing and security
water, sewer
 
Thank you very much for your reply.
Is the civil design basis the first deliverable for civil dept.? How will the civil design basis me made?
 
Landscape Plans
Plant Lists
Artwork Design (1% in some areas)
ADA Compliance Plans - Ramps & Rails
 
Steps in project development. The basis of design follows after a feasibility study. At this project stage a conceptual design is finalized, and the fundamental engineering parameters are identified. Contractors may be asked to use their own engineering design standards or adopt the standards of the project sponsors. The basis of design is a necessary step before issuing a formal front end engineering design (FEED) request to potential contractors.

The FEED is intended to further develop design, including detailed specifications and layout to get a more accurate cost estimate as a deliverable to the EPC bidding stage. The FEED identifies equipment and provides detail design of the project. The FEED contractor prepares engineering documents and bid packages to a sufficient level of detail to be used in the EPC bidding.

The EPC contractor is responsible for bringing a project to completion and start-up according to the project sponsors' design and specifications. The EPC award is followed by the process of detailed engineering and procurement.
 