liam1369
Structural
- Nov 13, 2014
- 73
Good Evening all,
I am a relatively new engineer and would like some clarification and guidance on a query I have in relation to NHBC guidance for trench foundation in cohesive clay soils.
Upon review of documentation and also discussing with other engineers. The terms 'minimum 1.0m deep trench foundations' often comes up.
However,
Is this stating the actual depth of the concrete trenches themselves need to be at least 1.0m deep, or does it simply mean 1.0m deep below existing ground level to underside of foundation? The top of new foundations are generally 450-600mm below ground level, so minimum 1000mm deep trenches will mean the foundation depth is already minimum 1450-1600mm below ground level.
To confuse matters anymore, I have read some references and heard from other engineers, that it needs to be at least 1000mm penetrating into the clay/cohesive soil. So if we have 0.50m top soil and 0.50m of sand/terrace deposits and then hit clay, it needs to go at least 1.0m into that. Whereas, in some references I have seen at least 200mm penetration mentioned.
If possible, is anyone able to provide clear guidance on the typical requirements in a clay soil and in layman terms, describe the actual methodology.
I have attached a sketch aiding with the explanation.
I appreciate any guidance and insight into this subject.
Many thanks,
Liam
I am a relatively new engineer and would like some clarification and guidance on a query I have in relation to NHBC guidance for trench foundation in cohesive clay soils.
Upon review of documentation and also discussing with other engineers. The terms 'minimum 1.0m deep trench foundations' often comes up.
However,
Is this stating the actual depth of the concrete trenches themselves need to be at least 1.0m deep, or does it simply mean 1.0m deep below existing ground level to underside of foundation? The top of new foundations are generally 450-600mm below ground level, so minimum 1000mm deep trenches will mean the foundation depth is already minimum 1450-1600mm below ground level.
To confuse matters anymore, I have read some references and heard from other engineers, that it needs to be at least 1000mm penetrating into the clay/cohesive soil. So if we have 0.50m top soil and 0.50m of sand/terrace deposits and then hit clay, it needs to go at least 1.0m into that. Whereas, in some references I have seen at least 200mm penetration mentioned.
If possible, is anyone able to provide clear guidance on the typical requirements in a clay soil and in layman terms, describe the actual methodology.
I have attached a sketch aiding with the explanation.
I appreciate any guidance and insight into this subject.
Many thanks,
Liam