1. air sampling system with sampling tubes at the ceiling and about half way down the room, same spacing for both.
2. smoke detectors at about the half way point down from the ceiling, mounted on large opening metal grid rail.
sequence is
a. two smokes set of system
or
b. one smoke, and air sampling alert, sets off system
anyone seen the smokes mounted more then a foot down and accepted it???