Close-out report on Basic Engineering of Oil&gas Flowstations upgrade 2

Status
Not open for further replies.

040365

Chemical
Jan 30, 2004
4
GB
I have being mandated to prepare a close-out report on Basic Engineering of Three Flowsations' upgrade Project for my discipline - Process Engineering. I want an input on how to go about it and the necessary areas to include as regard the Project.
 
Replies continue below

Recommended for you

What have you done? - Write it down, that is a close out report

You should include lessons learnt, on time, on budget, contractor performance, your performance, results of commissioning etc. Surley your superiors and/or colleagues can assist.

As part of the project close out you should AS BUILD all drawings and datasheets etc.

 
hi,

don't forget the basics,
the O&M manuals, guarantee
details, manufacturer's contact
details, recommended list
of spares, etc. etc.

cheers,
 