psychedomination
Structural
- Jan 21, 2016
- 114
Hi there,
I am designing a low wall to temporarily contain water, which will fill infrequently. The height of the wall will be 20". Typically I would go for a reinforced concrete wall when considering a liquid retaining structure but due to the wall being so short I was thinking of going the CMU block wall route with a suitable swellable waterbar and a thick render on the water facing side of the wall with a Xypex waterproofing agent. Due to the height, the water pressure is quite small. Using CMU should be faster and cheaper to construct.
I found some guidance on a detail for this system following the CIRIA guidelines in the "Masonry Bunds for Oil Storage Tanks.
See below typical details that I would most likely adopt (main difference is that I would have the vertical rebar post installed into the existing slab with straight embedment only and I will use an expanding water stop) :
However, I would like some advice on how to detail the connection between the new bund wall tying into the existing reinforced concrete block wall. Normally I would key the new wall into the existing but I'm not sure how this interface would work with a water stop. Instead of keying in, would it be a better detail to put in a post installed rebar dowels to connect the new bund to existing wall? Ideally, I don't really want to disturb the rebar in the existing wall much.
Any advice on an optimal detail in the situation to provide a waterproof joint with an expanding waterstop would be helpful.
For context see image below :
I am designing a low wall to temporarily contain water, which will fill infrequently. The height of the wall will be 20". Typically I would go for a reinforced concrete wall when considering a liquid retaining structure but due to the wall being so short I was thinking of going the CMU block wall route with a suitable swellable waterbar and a thick render on the water facing side of the wall with a Xypex waterproofing agent. Due to the height, the water pressure is quite small. Using CMU should be faster and cheaper to construct.
I found some guidance on a detail for this system following the CIRIA guidelines in the "Masonry Bunds for Oil Storage Tanks.
See below typical details that I would most likely adopt (main difference is that I would have the vertical rebar post installed into the existing slab with straight embedment only and I will use an expanding water stop) :
However, I would like some advice on how to detail the connection between the new bund wall tying into the existing reinforced concrete block wall. Normally I would key the new wall into the existing but I'm not sure how this interface would work with a water stop. Instead of keying in, would it be a better detail to put in a post installed rebar dowels to connect the new bund to existing wall? Ideally, I don't really want to disturb the rebar in the existing wall much.
Any advice on an optimal detail in the situation to provide a waterproof joint with an expanding waterstop would be helpful.
For context see image below :