bbookz
Structural
- Oct 19, 2005
- 27
I'm somewhat stumped with a CMU wall design. I'm designing a gym, mostly one story but has a partial mezzanine level. The walls are 12"CMU + cavity, insulation and brick (1'-6 3/4") total thickness.
There is a clerestory window essentially wrapping around the entire building. The window sill elevation/ top of wall is 20'-6".
On one side of the 150'x70'building I'm retaining 10'-8" max of soil. The other side is not retaining.
Because the wall is not connected to a diaphragm I decided it could be designed two ways as a cantilever or as pinned at the top by a girt. When I initially designed the project (It has been on hold 3 yrs) I determined that the cantilevered wall would not work for deflection. A rough calc., but I'm getting 1.29" wall tilt based on 100pci soil spring and .75" based on the wall deflection.
I placed 24"SQ concrete piers @ 17' o/c. The concrete piers support steel posts a few feet high which carry the roof framing. A steel channel girt frames into the bottom of the steel column which is anchored into the top of the pier. Essentially the concrete piers support the gravity load of the clear span roof, support the walls laterally and are the entire lateral system for the building. Deflection in the concrete piers based only on the lateral loading (no soil spring) is 0.75" max. I didn't take tilt into account (probably should). The pier is cantilevered with 284 k-ft max at the base. I have notes on the drawing for bracing and back-filling requirements.
The project came back to life and looking back at the concrete piers the load path just seems convoluted. The approach doesn't seem incorrect, but it just seems like it would be so much better if I could get the wall to work as all masonry. Any suggestions would be appreciated. I've attached an elevation.
There is a clerestory window essentially wrapping around the entire building. The window sill elevation/ top of wall is 20'-6".
On one side of the 150'x70'building I'm retaining 10'-8" max of soil. The other side is not retaining.
Because the wall is not connected to a diaphragm I decided it could be designed two ways as a cantilever or as pinned at the top by a girt. When I initially designed the project (It has been on hold 3 yrs) I determined that the cantilevered wall would not work for deflection. A rough calc., but I'm getting 1.29" wall tilt based on 100pci soil spring and .75" based on the wall deflection.
I placed 24"SQ concrete piers @ 17' o/c. The concrete piers support steel posts a few feet high which carry the roof framing. A steel channel girt frames into the bottom of the steel column which is anchored into the top of the pier. Essentially the concrete piers support the gravity load of the clear span roof, support the walls laterally and are the entire lateral system for the building. Deflection in the concrete piers based only on the lateral loading (no soil spring) is 0.75" max. I didn't take tilt into account (probably should). The pier is cantilevered with 284 k-ft max at the base. I have notes on the drawing for bracing and back-filling requirements.
The project came back to life and looking back at the concrete piers the load path just seems convoluted. The approach doesn't seem incorrect, but it just seems like it would be so much better if I could get the wall to work as all masonry. Any suggestions would be appreciated. I've attached an elevation.