sdz
Structural
- Dec 19, 2001
- 556
The constant additional complexity of the codes just adds work with little additional benefit.
When I started work many years ago (all in working stress & imperial measurements) I could keep 4 draftsmen on the go - that's using a slide rule!! Then the codes were A5 size and 10mm thick.
These days I am lucky to keep 1 & 1/2 draftsmen going.
Though the speed of drafting has increased because of CAD, the major reason for the change is the complexity of the codes and the need to check a 40 plus load cases (in Oil & Gas 120 plus) rather than the 3 or 4 you would have gauged to be the worst cases.
When the provisions for shear in slabs in the concrete code changed in about 1990 to be the same as beams (more conservative), I got onto one of the code committee and asked why the change as the American and British codes had not.
His response was that he agreed with me that the change was conservative and unnecessary but it had the advantage that now you only needed one formula to check shear in both beams and slabs!! Now in heavy foundation slabs you have to add shear reinforcement when previously you did not.
However though he did not agree with the change, he had 14 other points he wished to get through the committee so he had to compromise some where!!
So while our code committees comprise academics and representatives of manufactures and are under represented by "working design engineers" we are going to get more complex codes with additional conservatism, resulting in additional costs in construction and design without any true benifit.
The only way most of us understand the Concrete Code on the design of long columns is to buy "Reinforced Concrete" by Warner, Rangan and Hall - what a good way of making sure your book sells.
Some time ago the British Codes allowed you to use either Working Stress or Ultimate State design ( I don't know if this is the case still) - invariable most engineers used the simpler Working Stress. I believe that this choice should be the case here.
A few years ago the Institute of Structural Engineers in London did some checks of existing buildings using the Ultimate Stress method and found that they did not past muster. The buildings had been built only a few years earlier - designed using working stress. This caused a dilemma - which approach is right or is it just that one method is more conservative?
The only failures of "engineered structures" I have come across have been either due to poor detailing (stiffeners left out of bin ring girder at support point), lack of adequate maintenance (corrosion causing failure), increases in mechanical loads without a structural check, operator error, material fatigue/imperfection (in a stacker/reclaimer shaft) or ground movement. This is for structures built in the 60's to the present day.
Hope this give you food for thought as to how our code committees work and also gives vent to my cynicism
(reproduced with permission of author)
When I started work many years ago (all in working stress & imperial measurements) I could keep 4 draftsmen on the go - that's using a slide rule!! Then the codes were A5 size and 10mm thick.
These days I am lucky to keep 1 & 1/2 draftsmen going.
Though the speed of drafting has increased because of CAD, the major reason for the change is the complexity of the codes and the need to check a 40 plus load cases (in Oil & Gas 120 plus) rather than the 3 or 4 you would have gauged to be the worst cases.
When the provisions for shear in slabs in the concrete code changed in about 1990 to be the same as beams (more conservative), I got onto one of the code committee and asked why the change as the American and British codes had not.
His response was that he agreed with me that the change was conservative and unnecessary but it had the advantage that now you only needed one formula to check shear in both beams and slabs!! Now in heavy foundation slabs you have to add shear reinforcement when previously you did not.
However though he did not agree with the change, he had 14 other points he wished to get through the committee so he had to compromise some where!!
So while our code committees comprise academics and representatives of manufactures and are under represented by "working design engineers" we are going to get more complex codes with additional conservatism, resulting in additional costs in construction and design without any true benifit.
The only way most of us understand the Concrete Code on the design of long columns is to buy "Reinforced Concrete" by Warner, Rangan and Hall - what a good way of making sure your book sells.
Some time ago the British Codes allowed you to use either Working Stress or Ultimate State design ( I don't know if this is the case still) - invariable most engineers used the simpler Working Stress. I believe that this choice should be the case here.
A few years ago the Institute of Structural Engineers in London did some checks of existing buildings using the Ultimate Stress method and found that they did not past muster. The buildings had been built only a few years earlier - designed using working stress. This caused a dilemma - which approach is right or is it just that one method is more conservative?
The only failures of "engineered structures" I have come across have been either due to poor detailing (stiffeners left out of bin ring girder at support point), lack of adequate maintenance (corrosion causing failure), increases in mechanical loads without a structural check, operator error, material fatigue/imperfection (in a stacker/reclaimer shaft) or ground movement. This is for structures built in the 60's to the present day.
Hope this give you food for thought as to how our code committees work and also gives vent to my cynicism
(reproduced with permission of author)