longisland
Geotechnical
- Sep 25, 1999
- 82
Hi,
A post tensioned girder was poured with cold joints formed &
there is no proper construction joints. The incident happened
when one truck of the concrete was rejected since the slump
was only 2 inch. The next pour was 2 hours later but they claimed
it's okay since set retarders was added. The joint is visible at
35 degree across the beam. I have advised this beam is to be
abandoned but the contractor insisted the beam can be stressed.
This is the first time I've dealt with such a messy job.
What's going to happen if the beam is stressed?
Furthermore, I would like to know if there is any side effects
on the concrete if the plasticiser is overdosed. The contractor
poured 2 litres of plasticisers into the mixer truck loaded with
5 cubic yards of concrete when the slump was too low at 3 inch height.
The target 28 day strength of the concrete is 7000 psi.
Thanks for the input
A post tensioned girder was poured with cold joints formed &
there is no proper construction joints. The incident happened
when one truck of the concrete was rejected since the slump
was only 2 inch. The next pour was 2 hours later but they claimed
it's okay since set retarders was added. The joint is visible at
35 degree across the beam. I have advised this beam is to be
abandoned but the contractor insisted the beam can be stressed.
This is the first time I've dealt with such a messy job.
What's going to happen if the beam is stressed?
Furthermore, I would like to know if there is any side effects
on the concrete if the plasticiser is overdosed. The contractor
poured 2 litres of plasticisers into the mixer truck loaded with
5 cubic yards of concrete when the slump was too low at 3 inch height.
The target 28 day strength of the concrete is 7000 psi.
Thanks for the input