Oilisking
Civil/Environmental
- Dec 15, 2009
- 2
Hello all!
We are getting ready to pour a 3' thick mat on grade this week. Average temps for the pour days in the mid 20s, overnight lows in the teens. Based on the depth of the slab, I'm expecting some signifigant heat.
Right now the ground is not frozen, as temps are still around 40 degrees, but I expect it to be crusty on the pour date. Can I pour on a light crust, expecting the ground to thaw out quickly? I am "this close" to telling the contractor to heat the subgrade.
Also, is it worthwhile to cover the reinforcement without heating it?
FWIW, I am hesitant to heat the area due to the site restrictions, which would be poor for combustion heaters.
The contractor is confident that blankets are all that is needed. I am primarily concerned about the crunchy subgrade and any subsequent cracks/settling that may occur.
THANKS!
We are getting ready to pour a 3' thick mat on grade this week. Average temps for the pour days in the mid 20s, overnight lows in the teens. Based on the depth of the slab, I'm expecting some signifigant heat.
Right now the ground is not frozen, as temps are still around 40 degrees, but I expect it to be crusty on the pour date. Can I pour on a light crust, expecting the ground to thaw out quickly? I am "this close" to telling the contractor to heat the subgrade.
Also, is it worthwhile to cover the reinforcement without heating it?
FWIW, I am hesitant to heat the area due to the site restrictions, which would be poor for combustion heaters.
The contractor is confident that blankets are all that is needed. I am primarily concerned about the crunchy subgrade and any subsequent cracks/settling that may occur.
THANKS!