Collar Tie's

Status
Not open for further replies.

musick

Structural
Feb 13, 2015
2
Retired Contractor here.
My question is placement and size of collar ties.
Span is 25'3", 2x6 rafters. I have a "bearing" wall 13'6" from slab to rafters. Roughly 1'off center from 2x8 ridge.
My ties will connect to the wall studs as well as the rafters.
I had planned in the upper 1/3 making it 32" above the plates and a length of approx. 10'
Will this work? and size of ties?
Thank you for any advise.
 
Replies continue below

Recommended for you

Just to make sure we're using the same terminology, are you talking about rafter ties or collar ties? Connecting to the wall studs and rafters sounds like a rafter tie (usually a ceiling joist). But upper 1/3 would be a collar tie. Rafter tie keeps the gable from spreading, the collar tie fixes the ridge and keeps it from separating under unbalanced wind and snow loading.

You can draw out a sketch and it'll help. What was your trade? If you were a framer/carpenter, you should be able to get through the IRC easily enough. Conveniently enough you're in Virginia. So am I, so my references should work well for you. Here's a link to Chapter 8 of the Virginia Residential Code. It has tables that spell out span lengths and required sizes, as well as adjustments depending on variable heights of rafter ties.
 
Thank you phamENG
I was a framer for many years. I know the code use to state, collar ties in the upper 1/3 of attic space.
I read the code had changed to the lower 1/3 unless designed. Now, I think it may have been the IRC code changed, because from my understanding r802.4.6 states in the upper 1/3, exactly my plan. I realize I will need to sister the rafters.
anyway I will upload the print.
Thank you
collar_j5vneo.png
 
Ok - thanks for the sketch. So what you're proposing doesn't fit as nicely into the prescriptive code. Looks like you have pretty typical construction on one side, and a vaulted ceiling on the other. You'll need to do one of two things: use a ridge beam OR cantilever the joists on the right over the bearing wall and use the cantilever ends to support the rafters that don't have a rafter tie. Seems plausible, though.
 