I have an 11kV cable of about three (3) kilometer length installed between two facilities. Both facilities have their own power generation system and they are operating in island mode. This 11kV cable was originally intended to supply and standby power source for the black start of one facility from the other facility power supply. However, each facility has its own black start DG sets from the beginning. Hence this 11kV interconnection was never used. Not even energized/commissioned! The cable is lying un-used for the last 20 years.
Now we are intending to energise this cable. But people are not sure what are the tests required to establish the healthiness of the cable. If anyone can share your experience in similar set up, is highly appreciated. For your information, this is a offshore facility and it is a subsea (submarine) cable.
Now we are intending to energise this cable. But people are not sure what are the tests required to establish the healthiness of the cable. If anyone can share your experience in similar set up, is highly appreciated. For your information, this is a offshore facility and it is a subsea (submarine) cable.