NewNorthernGeotech
Geotechnical
- Apr 21, 2006
- 7
Here's a good one! (I think so anyways)
New project for me, weekend and no senior advice around, so I turn to the internet... GOD HELP ME!
We're constructing a containment area with 3:1 slopes on the inside berms. Nicely compacted rock fill as the base and beautiful till material being placed. However, we've removed oversized material for our key trench for permiability reasons, but left all oversize in it for the slopes because we will us a liner.
The issue! I'm QC and QA now wants to develop a method spec for the placement. Test strips are the plan with varying lift thicknesses, levels of compaction, yada yada yada.
Boulders visually range up to 600 mm and oversize content (larger then 20 mm) has to be up around 70 to 85%! Soil matrix is great, well graded with 25 to 30% silts/clays.
QUESTION 1: Density testing with nuclear device has been decided on and I personally question the usefullness based on the quantity of larger particles. I'll take an obscene amounts of readings and see if anything sensical comes out of it, but IS THERE A BETTER WAY!
QUESTION 2: Does the "Nuke" have to be flat? Or can I place it right on the 3:1 slope and get good readings. I'm headed out there shortly and plan to satisfy myself by spending some time, but am interested to see what sort of responses I get here!
QUESTION 3: ALSO! QA seems to be pressuring me to develope the procedure for this testing, since I don't believe it's the best solution and have to senior advice I'm reluctant. Monday is coming, but shouldn't QA be supplying me with the plan and I simply impliment and give out results??
THANKS!!
New project for me, weekend and no senior advice around, so I turn to the internet... GOD HELP ME!
We're constructing a containment area with 3:1 slopes on the inside berms. Nicely compacted rock fill as the base and beautiful till material being placed. However, we've removed oversized material for our key trench for permiability reasons, but left all oversize in it for the slopes because we will us a liner.
The issue! I'm QC and QA now wants to develop a method spec for the placement. Test strips are the plan with varying lift thicknesses, levels of compaction, yada yada yada.
Boulders visually range up to 600 mm and oversize content (larger then 20 mm) has to be up around 70 to 85%! Soil matrix is great, well graded with 25 to 30% silts/clays.
QUESTION 1: Density testing with nuclear device has been decided on and I personally question the usefullness based on the quantity of larger particles. I'll take an obscene amounts of readings and see if anything sensical comes out of it, but IS THERE A BETTER WAY!
QUESTION 2: Does the "Nuke" have to be flat? Or can I place it right on the 3:1 slope and get good readings. I'm headed out there shortly and plan to satisfy myself by spending some time, but am interested to see what sort of responses I get here!
QUESTION 3: ALSO! QA seems to be pressuring me to develope the procedure for this testing, since I don't believe it's the best solution and have to senior advice I'm reluctant. Monday is coming, but shouldn't QA be supplying me with the plan and I simply impliment and give out results??
THANKS!!