I have a situation where I must make a beam splice that requires the full section strength of the beam (CJP). The beam is a built up member with a flange thickness of 1.5" and a web thickness of 3/4". I am aware of the qualified welding requirements in AWS for this type of joint.
My question is:
1.) Do AWS or AISC require any sort of splice offset for the flange and web?
2.) Does the joint have to be a double bevel on both sides of the web?
3.) Are the weld access holes for beam copes required for splices as well?
Thank you.
My question is:
1.) Do AWS or AISC require any sort of splice offset for the flange and web?
2.) Does the joint have to be a double bevel on both sides of the web?
3.) Are the weld access holes for beam copes required for splices as well?